top of page
PROCUREMENT
Learn about the bid packages for the Care Pavillion project. Download meeting presentations and attendee lists.
PRE-PROPOSAL MEETINGS
BID PACK #3
JANUARY 10, 2023
BID PACK #4
JUNE 8, 2023
BID PACKAGES
Bid Package | Release Date | Scope | Awarded |
---|---|---|---|
#1 | October 2022 | DIRTT Walls | The Berg Group |
#2 | October 2022 | Mechanical/Plumbing | Harris |
#2 | October 2022 | Electrical | Parsons |
#3 | January 2023 | Earthwork | Bolander |
#3 | January 2023 | Curtainwall | Empirehouse |
#4 | June 2023 | Concrete (ready mix supply, rebar supply, PT supply, rebar install, forming, pumping) | TBD |
#4 | June 2023 | Waterproofing | RAM Construction Services |
#4 | June 2023 | Rebar Supply | CMC Steel Fabricators |
#4 | June 2023 | Rebar Install | Woody’s Rebar |
#4 | June 2023 | Metal Panel/Terracotta | MG McGrath |
#4 | June 2023 | Fire Protection | Viking Automatic Sprinkler |
#5 | August 2023 | Remaining Enclosure | TBD |
#5 | August 2023 | Structure | TBD |
#5 | August 2023 | Roofing | TBD |
#6 | October 2023 | Drywall | TBD |
#6 | October 2023 | Finishes | TBD |
#6 | October 2023 | Site Improvements | TBD |
bottom of page